PUBLISHING HOUSE

Fit Out of 17 floors including new mezzanine floor
and adaptations to slab.

Diamond Drilling
Builderswork

Client

ISG PLC

Due to the overlap of base build and Fit Out, there were often logistical issues with the larger material deliveries and internal distribution. Working alongside the logistics managers, advanced look ahead schedules for bookings and taking a flexible approach to working shifts meant that we were able to stay on programme.
We worked with Briggs Amasco, the base build roofing contractor, to deliver the roofing system and successfully coordinated with all other trades to install the mezzanine steelwork to a challenging Level 2 programme whilst maintaining the quality and health & safety standards expected by ISG.
Structural fire protection was provided by on & off site spraying techniques. Due to the nature & high fire protection rating required of the intumescent application, we utilized the winter garden area and ventilated PPE to mitigate the health risks of inhalation.