Scope
Strip out, structural works, steel works and builders
Description
LDD’s package involves the strip out of the old Benneton shop plasterboard partitions, escalators and screed over 4 floors.
It was important that caution was taken removing stud was to prevent any damage to heritage ceilings and column behind. This was also an important factor during the fit-out stages, ensuring nothing was knocked or removed accidently new steel work for structural strengthening, lift shafts, risers and plant gantries. Screeding through floors, fire curtains and basement dam proofing
Key factors include working around heritage ceilings and columns, logistical issues, very tight program and small footprint Design change was a familiar obstacle and reacting to these changes and updates along with communication and coordination was essential to ensuring hand over for the store opening.
Drilltec
Listed Building
£50K
6 weeks
Up to 6 Operatives